Friday 14 September 2012

12th Sep - Concrete floors laid!

Poured concrete floors of workshop/ working space

Frazer demonstrating how the surviving wall falls apart by touching!



10th Sep - Drainage

Drainage going in for workshop

7th Sep Foundations

Foundations starting!

Blocks being laid with cavity - we loose 100mm around inside of  these rooms due to having to fit in with regulations of a newbuild! Shame.


4th September - Skip day!

A lot of soil and hardcore to remove before foundations go in

Hole being made where doorway through to garden will be

Chimney being re-built! Yey!

Frazer making room for skip

Fireplace revealed in gallery

12 skip loads!